Turnaround Status Report — Calder Bay · Weller Parish · Olefins Unit
8/3/26 – 9/6/26
Generated 8/31/26
Total equipment
20
Complete
7
35%
Open RRs
7
RRs closed
2
Discovery
7/15
equipment
Progress by asset type
Asset type
In scope
Complete
%
Discovery
Open RRs
Drums & Tanks
6
2
33%
3/6
2
Exchangers
5
1
20%
2/5
2
Towers
4
1
25%
2/4
2
PSV / PSE Pull
5
3
60%
—
0
Piping & valve packages
—
—
—
—
1
Total
20
7
35%
7/15
7
RRs by cause
8 total
Mechanical damage113%
Corrosion338%
Erosion113%
Cracking225%
Other113%
Repair recommendations — written vs closed
Asset type
Written
Closed
Open
Exchangers
4
2
2
Drums & Tanks
2
0
2
Towers
2
0
2
Piping & Valves
1
0
1
Total
9
2
7
Open repair recommendations
RR #
Equipment / package
Asset type
Finding
Written
Status
OLE-RR 002
D-215
Drums & Tanks
Bottom head general thinning below t-min over a band roughly 14 inches wide at the 6 o'clock position. Weld overlay or insert plate required before return to service.
8/11/26
Approved
OLE-RR 002 REV 1
D-215
Drums & Tanks
Revision 1: insert plate extended to 22 inches after the second UT pass found the thin band running further toward the 4 o'clock position.
8/19/26
Awaiting review
OLE-RR 003
C-407
Towers
Packing support ring welds cracked at three positions. Grind out and re-weld, PT the finished welds.
8/13/26
Approved
OLE-RR 004
PKG-14 Quench Water Header
Piping & Valves
Quench water header elbow at the 14 inch tee shows external wall loss under a failed coating. Replace the spool.
8/15/26
Awaiting review
Closed repair recommendations are not listed. 2 of 9 written to date have been closed out.
Equipment still outstanding
Drums & Tanks · 4 outstanding
D-206
Charge Gas Suction Drum
In progress
D-210
Propylene Refrigerant Receiver
In progress
D-212
Fuel Gas Knockout Drum
Not started
D-215
Spent Caustic Surge Drum
Repair
Exchangers · 4 outstanding
E-301
Charge Gas Aftercooler
Repair
E-304
Quench Water Cooler
In progress
E-312
Depropanizer Reboiler
In progress
E-316
Caustic Circulation Cooler
Not started
Towers · 3 outstanding
C-403
Deethanizer
In progress
C-405
Depropanizer
In progress
C-407
Caustic Scrubber
Repair
PSV / PSE Pull · 2 outstanding
PSV-1180
Propylene Receiver Relief
In progress
PSV-1206
Fuel Gas KO Drum Relief
Not started
Vantage Turnaround Wallchart · Calder Bay · Weller Parish · Olefins Unit · This report is generated live from the digital wallchart.
OLE-RR 005
E-312
Exchangers
Crack indication in the channel nozzle-to-shell weld, 1.8 inches long. Excavate, re-weld and PT.
8/21/26
Awaiting review
OLE-RR 006
C-403
Towers
Tray 12 downcomer sag of roughly 0.75 inches. Recommend replacement at the next opportunity, not this outage.
8/22/26
Deferred
OLE-RR 009
E-304
Exchangers
Inlet-pass tube-end erosion. Plug 14 tubes and install ferrules on the remaining inlet pass.