Turnaround Status Report — Calder Bay · Sabine Terminal · Tank Farm B
7/6/26 – 8/15/26
Generated 8/31/26
Progress by asset type
| Asset type | In scope | Complete | % | Discovery | Open RRs |
|---|
| Storage Tanks | 5 | 2 | 40% | 4/5 | 2 |
| Total | 5 | 2 | 40% | 4/5 | 2 |
Repair recommendations — written vs closed
| Asset type | Written | Closed | Open |
|---|
| Storage Tanks | 2 | 0 | 2 |
| Total | 2 | 0 | 2 |
Open repair recommendations
| RR # | Equipment / package | Asset type | Finding | Written | Status |
|---|
| TKF-RR 001 | TK-226 | TANKS | Underside floor pitting near the sump. Recommend a 10 ft by 10 ft patch plate over the affected area. | 7/30/26 | Approved |
| TKF-RR 002 | TK-230 | TANKS | Nozzle N4 reinforcing pad weld is undersized against the original drawing. Recommend re-welding to the specified leg size. | 8/7/26 | Awaiting review |
Closed repair recommendations are not listed. 0 of 2 written to date have been closed out.
Equipment still outstanding
Storage Tanks · 3 outstanding
| TK-226 | Slop Oil, 20,000 bbl | Repair |
| TK-228 | Diesel Storage, 45,000 bbl | In progress |
| TK-230 | Reformate Storage, 45,000 bbl | Repair |
Vantage Turnaround Wallchart · Calder Bay · Sabine Terminal · Tank Farm B · This report is generated live from the digital wallchart.