RR Log
Global chronological numbering — RR # order is written order, numbers are never reused.
Export CSV
Log activity
Total
3
Filtering
Awaiting review
2
Filtering
Approved
1
Filtering
Deferred
0
Filtering
Closed
0
Filtering
Filter:
Last 24 hours
Last 7 days
Last month
All
All asset types
EXCHANGERS
PIPING VALVES
All equipment
E-520
E-528
PKG-6 Reactor Effluent Line
All causes
Mechanical damage
Corrosion
Erosion
Cracking
Other
Not tagged
3 of 3 - numbers never reused
RR #
Equipment
Asset type
Finding
EWO #
Written by
Written
Status
HDS-RR 001
E-528
EXCHANGERS
Eleven tubes beyond the plugging limit. Recommend partial retube of the outer two rows.
—
Ingrid Salas
8/20/26
review
HDS-RR 002
E-520
EXCHANGERS
Shell course 2 UT reading trending down. Recommend an additional CML grid at the next internal.
—
Nolan Prejean
8/22/26
approved
HDS-RR 003
PKG-6 Reactor Effluent Line
package
PIPING VALVES
Support shoe corrosion under insulation at three hangers on the reactor effluent line.
—
Ray Thibodeaux
8/23/26
review