Vantage Integrity GroupContractor name and branding hidden for privacy
Internal Status Report — Calder Bay · Weller Parish · Olefins Unit
Internal — not for client distribution
8/3/26 – 9/6/26
Generated 8/31/26
Total equipment
20
Complete
7
35%
Open RRs
7
RRs closed
2
Discovery
7/15
equipment
Progress by asset type
Asset type
In scope
Complete
%
Discovery
Open RRs
Drums & Tanks
6
2
33%
3/6
2
Exchangers
5
1
20%
2/5
2
Towers
4
1
25%
2/4
2
PSV / PSE Pull
5
3
60%
—
0
Piping & valve packages
—
—
—
—
1
Total
20
7
35%
7/15
7
RRs by cause
8 total
Mechanical damage113%
Corrosion338%
Erosion113%
Cracking225%
Other113%
Repair recommendations — written vs closed
Asset type
Written
Closed
Open
Exchangers
4
2
2
Drums & Tanks
2
0
2
Towers
2
0
2
Piping & Valves
1
0
1
Total
9
2
7
Repair recommendation log
RR #
Equipment / package
Asset type
Finding
Written
Status
OLE-RR 001
E-301
Exchangers
Gasket seating surface on the stationary tubesheet is scored across three pass-partition lands. Machine the face back to a flat, continuous surface.
8/8/26
Closed
OLE-RR 002
D-215
Drums & Tanks
Bottom head general thinning below t-min over a band roughly 14 inches wide at the 6 o'clock position. Weld overlay or insert plate required before return to service.
8/11/26
Approved
OLE-RR 002 REV 1
D-215
Drums & Tanks
Revision 1: insert plate extended to 22 inches after the second UT pass found the thin band running further toward the 4 o'clock position.
8/19/26
Awaiting review
OLE-RR 003
C-407
Towers
Packing support ring welds cracked at three positions. Grind out and re-weld, PT the finished welds.
8/13/26
Approved
Equipment status by asset type
Drums & Tanks · 6 in scope
D-201
Quench Water Accumulator
Complete
D-204
Caustic Wash Drum
Complete
D-206
Charge Gas Suction Drum
In progress
D-210
Propylene Refrigerant Receiver
In progress
D-212
Fuel Gas Knockout Drum
Not started
D-215
Spent Caustic Surge Drum
Repair
Exchangers · 5 in scope
E-301
Charge Gas Aftercooler
Repair
E-304
Quench Water Cooler
In progress
E-308
Propylene Condenser
Complete
E-312
Depropanizer Reboiler
In progress
E-316
Caustic Circulation Cooler
Not started
Towers · 4 in scope
C-401
Demethanizer
Complete
C-403
Deethanizer
In progress
C-405
Depropanizer
In progress
C-407
Caustic Scrubber
Repair
PSV / PSE Pull · 5 in scope
PSV-1102A
Quench Tower Overhead Relief
Complete
PSV-1102B
Quench Tower Overhead Relief (spare)
Complete
PSV-1145
Caustic Wash Drum Relief
Complete
PSV-1180
Propylene Receiver Relief
In progress
PSV-1206
Fuel Gas KO Drum Relief
Not started
Administrative notes — internal
D-215
Owner asked for the wall-loss trend against the 2023 readings before the repair scope is priced. Not for the client packet.
Rolling log
Date
Shift
Inspector
Equipment
Details
8/23/26
Days
Ingrid Salas
E-304
Tube-end erosion quantified. RR written for plugging and ferrules.
8/23/26
Days
Nolan Prejean
PSV-1145
Shop test complete, seat lapped, reinstalled.
8/22/26
Nights
Curtis Haney
D-210
Drum opened, internal VI complete. UT scheduled.
8/22/26
Nights
Sonia Barrera
C-403
Upper section VI complete. Tray 12 downcomer sag noted, RR written.
8/21/26
Nights
Wes Duplantis
E-312
Shell VI and UT complete. Bundle still in the cleaning rack.
8/21/26
Nights
Wes Duplantis
E-312
Channel nozzle weld crack found on PT. RR written.
8/20/26
Nights
Sonia Barrera
D-206
Internal VI complete. Mesh pad sagging on the north side.
8/19/26
Vantage Turnaround Wallchart · Calder Bay · Weller Parish · Olefins Unit · INTERNAL record — includes closed repairs, completed equipment and administrative notes. Not for client distribution.
OLE-RR 004
PKG-14 Quench Water Header
Piping & Valves
Quench water header elbow at the 14 inch tee shows external wall loss under a failed coating. Replace the spool.
8/15/26
Awaiting review
OLE-RR 005
E-312
Exchangers
Crack indication in the channel nozzle-to-shell weld, 1.8 inches long. Excavate, re-weld and PT.
8/21/26
Awaiting review
OLE-RR 006
C-403
Towers
Tray 12 downcomer sag of roughly 0.75 inches. Recommend replacement at the next opportunity, not this outage.
8/22/26
Deferred
OLE-RR 007
E-301
Exchangers
Shell-side inlet nozzle internal corrosion. Blend grind and re-measure.
8/7/26
Closed
OLE-RR 009
E-304
Exchangers
Inlet-pass tube-end erosion. Plug 14 tubes and install ferrules on the remaining inlet pass.
8/23/26
Awaiting review
Days
Ingrid Salas
E-304
Bundle and channel VI complete. Tube-end erosion noted.
8/19/26
Days
Ray Thibodeaux
E-301
Tubesheet machining complete and accepted. RR closed.
8/18/26
Days
Ingrid Salas
E-304
Shell VI complete. Bundle out for cleaning.
8/16/26
Days
Nolan Prejean
E-308
Hydro passed. Exchanger released for reinstallation.
8/15/26
Days
Nolan Prejean
C-401
PT of the feed nozzle welds complete, no indications.
8/15/26
Days
Nolan Prejean
PKG-14
Coating disbonded on the quench water header elbow. RR written.
8/14/26
Nights
Wes Duplantis
E-308
Bundle ECT complete, no plugging required.
8/14/26
Days
Ray Thibodeaux
C-401
Internal VI top to bottom. Two downcomer bolts replaced.
8/13/26
Nights
Curtis Haney
C-407
PT confirms cracking at three positions. RR written.
8/13/26
Days
Ingrid Salas
D-204
Bottom head UT complete, no findings.
8/12/26
Nights
Curtis Haney
C-407
Internal VI complete. Support ring cracking suspected.
8/12/26
Days
Ingrid Salas
D-204
Internal VI complete. Weir plate clean after hydroblast.
8/11/26
Days
Nolan Prejean
D-201
Shell UT at 12 CMLs, all above t-min.
8/11/26
Days
Ray Thibodeaux
D-215
UT confirms thinning below t-min. RR written.
8/10/26
Days
Ray Thibodeaux
D-215
Internal VI complete. Bottom head thinning suspected, UT ordered.
8/9/26
Days
Ray Thibodeaux
D-201
Internal VI complete. No findings.
8/8/26
Days
Ray Thibodeaux
E-301
Tubesheet gasket face scored. RR written for machining.
8/7/26
Nights
Wes Duplantis
E-301
Channel and bundle VI complete. 6 tubes plugged.
8/7/26
Days
Ray Thibodeaux
E-301
Shell inlet nozzle pitting found. RR written for a blend grind.
8/6/26
Days
Ray Thibodeaux
E-301
Shell internal VI complete. Light general corrosion, acceptable.
8/5/26
Days
Ray Thibodeaux
E-301
Bundle pulled and sent to the cleaning rack. Shell entry permit opened.