| TK-221 | Naphtha Storage, 80,000 bbl | | TKF | API 653 internal complete, returned to service 8/09. | Internal visual, floor MT scan, shell course UT. | WD 07/14 | WD 07/17 | · | · | Floor scan clean. |
| TK-224 | Gasoline Blend Stock, 60,000 bbl | | TKF | Complete, returned to service 8/12. | Internal visual, floor MT scan. | SB 07/20 | SB 07/22 | · | · | · |
| TK-226 | Slop Oil, 20,000 bbl | 1 open RR | TKF | Floor plate repair recommended. | Internal visual, floor MT scan, sump condition. | RT 07/28 | RT 07/30 | TKF-RR 001RR-001 | · | Underside pitting near the sump, see RR-001. |
| TK-228 | Diesel Storage, 45,000 bbl | | TKF | Roof seal inspection outstanding. | Internal visual, floor MT scan, primary seal survey. | CH 08/04 | ● | · | · | · |
| TK-230 | Reformate Storage, 45,000 bbl | 1 open RR | TKF | Shell nozzle reinforcement recommended. | Internal visual, floor MT scan, nozzle survey. | CH 08/06 | CH 08/07 | TKF-RR 002RR-002 | · | Nozzle N4 reinforcing pad weld undersized. |